Datasheet page: https://vutlan.atlassian.net/wiki/spaces/DEN/pages/2917203982/VT604t+Switched+Power+Distribution+Unit

Product page: https://vutlan.com/power-distribution-units/186-vt604t-switched-ip-pdu-with-4-outlets.html

...

Drivers: https://vutlan.atlassian.net/wiki/spaces/DRIV/pages/2912583997/Latest+Vutlan+drivers+for+T+series+VT325t+VT335t+VT825t+VT855t

...

Function and purpose

Function and purpose

VT604t / Switched PDU with 8 4 Outlets is a versatile power distribution unit designed for effective load management in various environments. It enables users to switch on, off, or reboot up to eight individual outlets, providing flexible control over connected devices.

...

Virtual sensors include PING, timers, triggers, Logic schemes, SNMP GET, x4 IP cameras, Virtual math elements, and others.

...

Use cases

The VT604t / Switched PDU with 4 Outlets is designed for a variety of use cases, making it an essential tool in environments that require reliable power management and environmental monitoring. Here are some of its key applications:

...

These use cases illustrate the versatility and importance of the VT608t in modern IT and facility management, helping organizations maintain operational efficiency, safety, and reliability. For more detailed information, you can check the Vutlan product page directly.

Physical Description

Front panel:

...

Back panel:

...

1. "1U 19-inch brackets" - x2 pcs for mounting brackets into a 1U 19" rack slot.

...

19. "CAN 1 / CAN 0" - Two digital connectors RJ12 for the connection of CAN sensors/extensions/devices on a CAN bus. Modules connected to these connectors can be chained together. Read the instructions at "CAN devises connection", and "Setting up CAN".

20. "SD card" - MicroSD card slot with an ejector. The card is needed for data storage or the "system restore". Read instructions at "Saving system logs to SD card", and "Restore of the appliance (for VT960 series)".

...

  • Normal mode: The switch is switched to the left ←. The switch should be always in this position.

  • Restore of appliance: The switch is switched to the right →. Used to load the clean system image from an SD card. Read the instructions at “Restore of appliance”.

Connection overview diagram

...

Power Supply Priorities

...

Power supply line

Description

1

  1. 110-240V AC

This is the main power supply line. The system chooses the power supply input with the biggest Voltage. That is why this power line always has the highest priority.

2

  1. 12V DC

This power line has the second priority and will start working only if there’s a power outage on power line 1.

Normally each of these lines supply the system with 11V. Power switching is instant.

3

  1. 9V DC

This power line has the lowest priority because it has the lowest voltage.

VT-ACCU or VT-BAT can be connected on this power line.

VT-ACCU is charged by the power line 1. The system will start working from VT-ACCU only in case power lines 1 and 2 fail (power outage).

VT-BAT battery is not charged. Once it is depleted, the battery has to be manually changed.

Drawing dimensions

...

19” 1U installation in a rack-cabinet

1.1

x2 19” brackets should be located in the package together with the system. Use x3 M3 screws to mount the brackets on each side of the unit.

1.2

 

2

 

Use x4 captive nuts and x4 M6 Screws to attached the unit to the rack.

Installing VT485m / RTU modem extension slot

VT855t has a slot for an extension. You can install only one module in this slot. You can install the “VT485m / Modbus RTU modem extension slot” or the “VT485r / OSDPv2 reader extension slot”. Both modules are ordered separately.

Extension

Photo with the module installed

VT485r

VT604t Switched PDU with monitoring 4 outlets with monitoring (back VT485r OSDPv2 reader slot extension).png

VT485m

VT604t Switched PDU with monitoring 4 outlets with monitoring (back VT485m Modbus RTU slot extension).png

Installing LTE slot modem

VT855t has a slot for “VT740 / LTE slot modem”. The modem is ordered separately.

Extension

Photo

VT740

 

VT604t Switched PDU with monitoring 4 outlets (front)(VT740 LTE slot modem).pngVT604t Switched PDU with monitoring 4 outlets (front)(VT740 LTE slot modem antennas).png

Installing reservation battery

The unit has an “Extension battery slot” at the back of the unit. You can install VT-BAT / Reservation battery 6F22 9V or VT-ACCU / Rechargeable reservation battery.

...

Note

Warning! If you install VT-ACCU or VT-BAT inside the system with charged batteries and decide to ship it. The system will be operational until the batteries are drained while in transit.

Configuring outlets

Read more at:

https://vutlan.atlassian.net/wiki/spaces/DEN/pages/1016363/Relay+switching+NC+NO+Outlets+switching

API: Switching devices

Read more at:

https://vutlan.atlassian.net/wiki/spaces/API/pages/335904815/Switching+devices

Package content

Include Page
VT604t package content
VT604t package content

Technical details

See a comparison table with technical details for each Vutlan PDU and monitoring unit at:

Comparison chart: PDUs

Frequently asked questions

Problem

Cause

Solution

Problem

Cause

Solution

The unit is not powering up.

The DIP switch is switched to the “R” position.

Switch the DIP switch to “N” position (Normal).

 

 

 

...